CITY OF LOWELL: Project Updates for Week of July 12

Update450

City of Lowell issued the following announcement on July 11.

Project Updates for Week of July 12

1. Road: 68th Street

 Cherry Valley Avenue to Thornapple River Drive

July 12 - October 3, 2021

Closed to through traffic; detour posted

Contractor:  Kentwood Excavating

Projected Cost:  $1,250,000 

About: Reconstruction to a two-lane, all-season road standard.  Work includes tree removal, HMA removal, concrete pavement removal, storm sewer work, culvert extension, concrete curb and gutter work, HMA paving, pavement marking and restoration.

2. Road: Alden Nash Avenue

Fulton Street to Foreman Street

July 12 - July 26, 2021

Closed to through traffic; detour posted

Contractor:  Superior Asphalt

Projected Cost: $353,600

About: This project is a crush & shape improvement project, which is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt.

Original source can be found here.

Source: City of Lowell

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS